下载后可任意编辑METHOD STATEMENT FOR BRIDGE, MICRO PILING, LOAD TEST AND CONCRETE WORKSCONSTRUCTION METHOD FOR THE BRIDGEOBJECTIVEThe objective of this method statement is to describe and outline a working methodology to ensure a fair degree of control, attention and consideration had been given to the construction of Bridge over Sg. Dapu, Sarawak.SCOPE OF WORKThe scope of work will cover the work methodology for:o Site Preparation o Pilling Work (Bored Pile)o Testing of Piles (PDA, Load Test and Pile Integrity Test*) o Construction of Foundation o Construction of Abutment o Construction of Pier o Construction of Girder Beam o Launching of Girder Beam o Construction of Bridge Deck o Finishing workWORK METHODOLOGY SITE PREPARATIONa.Prior of any construction being carried out, location for the construction of the bridge shall be identified and check by the surveyor.b.R.O.W. shall be verified to ensure no construction of permanent and temporary structures are out of the site boundaries.c.If the required area for construction is insufficient, negotiation with adjacent landowner shall be conducted for the rental of the land for bridge construction activities.d.Temporary crossing over different river shall be identified, assessed and constructed based on the most suitable solution available for each river crossing.e.In order for the construction of the bridge abutment and pier, a working platform shall be constructed.f.The surveyor shall identify and set on site the location of the abutments/piers for the bridgework.g.For the abutment or pier which is located at the riverbank or in the river, working platform shall be constructed by extension of the river outwards to the river.h.Suitable fill material from the earth...