Lidong aromatics complex project 技术标 第二章 项目组织机构 THE SECOND CONSTRUCTION OF SINOPEC 第 1 页 中国石化集团第二建设公司 第三章 施工部署 Chapter III Construction Arrangement 1.0 施工总体部署 General construction arrangement (一) 指导方针 Guiding principles 全面控制 持续创新 诚挚服务 顾客满意 All-round control, sustained innovation, cordial service, and satisfaction to customers ——是全体员工信守的准则 is the guideline abided by the whole staff (二) 施工部署 Construction Arrangement (1) 执行国家建委基本建设项目经理管理法,并贯彻公司对项目工程实行项目总承包的原则,项目经理部统一组织对内、对外的协调指挥,集中公司优势力量,组织会战。在合同工期内,高速、安全、优质建成该项目,确保开车投产一次成功。 To enforce the Project Manager Administrative Law of Fundamental Construction Projects of the National Construction Committee, and implement the principle that the company acts as the overall contractor of project construction works. The project manager shall be responsible to organize the internal and external coordination and commanding works in unison, and concentrate superior forces on the construction, so as to complete this project quickly, safely, with high quality and within the contracted construction period, and to ensure the success start-up and operation in single time. (2)在现场附近就近设置储罐预制厂,以减少运输工作量,最大限度为本工程服务。 Lidong aromatics complex project 技术标 第二章 项目组织机构 THE SECOND CONSTRUCTION OF SINOPEC 第 2 页 中国石化集团第二建设公司 Set up a tank prefabricating plant nearby the site, to reduce the transportation work and serve the project to the maximum extent. (3)集中公司精兵强将,对施工机具设备进行重点保障,并且费用给予优惠。 Concentrate the selected employees of better skills on the provision and maintenance of c...