1 目 录 1 .工程概况 ................................................................................................................ 2 2 .编制依据 ................................................................................................................ 2 3 .泵单试情况一览表 ................................................................................................ 2 4 .试运前的准备工作 ................................................................................................ 4 5 .单机试运应具备的条件 ........................................................................................ 4 6 .泵单机试运的几点说明及流程 ............................................................................ 5 7 .机泵的单机试运 .................................................................................................... 6 8 .安全保证措施 ........................................................................................................ 7 9 .试车计划安排 ........................................................................................................ 8 1 0 .计量器具及手段用料 .......................................................................................... 9 1 1 .附图 .................................................................................................................... 1 0 2 1.工程概况 中石化安庆分公司含硫原油加工适应性改造及油品升级工程—200 万吨/年催化裂化装置有各种类型泵 61 台,加药及注入系统 6 套,整体安装。 单机试运主要是对这些设备的制造及安装质量、机械性能等进行综合检验,同时也对附属的工艺管道、电气、仪表等专业设计及安装情况进行检验;通过单机试运也可完成部分管道的水冲洗工作。单机试运是一项复杂的多工种共同配合完成的工作,因而应加强组织工作,应有专人负责机泵的单机试运工作;且试运时制造厂家必须有专人在试运现场进行指导。 2.编制依据 2.1 200 万吨/年催化裂化装置施工组织设计 2.2《风机、压缩机、泵安装工程施工及验收规范》 GB50275-2010 2.3《石油化工机器设备安...