INSPECTION DIVISION W ORK INSTRUCTION Document No.: WI-CRI-HKG-IE-001 Title: General Inspection Criteria Revision No.: 008 Date: 22 February 2006 Inspection Service: DPI & FRI Page 1 of 15 Intertek Testing Services Ltd. Revision Revision Details No. Date 001 30 March 2000 Initial Release 002 29 April 2000 - “Individual of the following items are uses only when procedure or criteria are not specified by in the applicant’s “Requirement”.” Added on Scope. - 3.2 Packaging Check had been revised. - 3.3 Printing and Label Check had been revised. - 4.1 to 4.9 Procedure and criteria had been revised - 4.10 to 4.14 were deleted - Polarity check on U.S. lamp holder was added - Temperature rise check on motor by resistance method was added 003 25 May 2000 4.2.2 b. Added “Either resistance tester or indicating device can be used.” 4.8.1 Added “Inspect the sample as soon as powered-off (heated condition)” 4.11.1 a. Deleted “(Wheatstone bridge is recommended)” 4.11.1 d. Added “Measure and record individually the resistance of windings respectively by multi-meter”. 004 28 June 2000 - 4.2.2. b. Deleted to use the ohmmeter and buzzer device for Earth Continuity check. - Added the functional check item 4.12. - 4.9.1 and 4.10.1 added the rub test and tape check for electro-plating. 005 14 July 2000 Added the reference standard on the Hi-voltage check & Earth continuity check. 006 8 April 2003 - 4.5.2 Delete the statement “normally check only the maximum setting”. - Internal check (4.6) & barcode readability check (4.7): change the sample method from S2 to fix sampling size 5 units. - 4.7.2. Correct statement and add acceptance criteria for label and printing. - 4.9.1.b Add +/- 1...