产业园大道工程(一期)桩板墙支护施工方案目 录1、工程概况...................................................................12、工程特点与工艺选择.........................................................13、施工准备与工期目标.........................................................23.1 施工技术准备..........................................................23.2 物资条件准备..........................................................23.3 施工机械准备..........................................................33.4 工期目标..............................................................34、施工方法...................................................................34.1 混凝土方桩施工........................................................34.2 冠梁施工.............................................................104.3 挡土板施工...........................................................125、质量控制..................................................................155.1 方桩质量控制.........................................................155.2 钢筋工程质量控制.....................................................165.3 模板工程质量控制.....................................................175.4 混凝土浇筑质量控制...................................................196、 安全措施.................................................................206.1 安全保证措施.........................................................206.2 土方开挖安全措施.....................................................206.3 钢筋工程安全措施.....................................................216.4 模板支撑与拆除安全措施...............................................216.5 混凝土施工安全措施...................................................217、环保措施..................................................................218、雨季施工措施..............................................................221、工程概况本工程为广清产业园华清产业大道工程(一期)桩板墙支护工程,起点桩号为K5+710,终点桩号为 K5+...