目 录 、壱工程概况 ································································· 1 、弐工程地质情况 ··························································· 2 参、 土洞(溶洞)充填灌浆施工关键点 ···································· 7 四、 袖阀管法灌浆再加固方案 ············································ 10 四、 施工组织方案 ··························································· 13 伍、 质量确保方法 ··························································· 15 六、 安全施工方法 ··························································· 16 七、 文明施工方法 ··························································· 17 八、 附关于地质资料及基础平面图 一、 工程概况 建设单位:XXXXX 设计单位:XXXXX 勘察单位:XXXXX 监理单位:XXXXX 施工单位:XXXXX XXXX 位于 XX 市街口,东临 XX 市 XX 塔,北临 XX 村,南临 XX 河。三期高层 R-e-7~9 栋位于小区东北侧,该栋号为地下 1 层,地上 27 层,建筑高度 83.8m,基底面积 1709.36,建筑面积㎡39626.23。基础形式为㎡静压预应力混凝土管桩,桩型为 PHC-500AB(125)-C80,单桩竖向承载力特征值为 KN,部分单层地下室为抗拔桩,单桩竖向抗拔承载力特征值为350KN,要求桩端持力层为强风化粉砂岩,桩端进入持力层≥1m。 依照地质勘探资料,场地存在土洞及溶洞,其大小不一,分布亦无规律;经探明土洞 3 处、溶洞 2 处。为确保建筑物安全,必须给予土洞(溶洞)进行处理。 因为三期已建栋号 R-c-1~3 及 R-d-1~3 栋均存在着土洞(溶洞),且已成功顺利地处理这类不良地责问题,处理方案为灌浆处理。所以,依照之前施工经验, R-e-7~9 栋亦拟做相同处理方案:(1)地质勘察已探明土洞、...