1:一个项目连续错过交付日期,项目团队评估完该情况后,项目经理意识到团队绩效差的原因在于团队成员对于自己的职责缺乏清楚认识
项目经理首先应该关注哪一项
A project has consistently missed the delivery dates
After assessing the situation with the project manager realizes the poor performance is due to a lack of charity for team member’s responsibilities
What should the project manager focus on first
A:创建 RACI 图Create a RACI chartB:巩固领导团队的角色Consolidate the role of the leadershipC:协商获得具有更高技能的新团队成员Negotiation for new team member with stronger skillsD:使用奖励和强制权利激励成员Use reward and coercive power to motivate the team正确答案:A 解析:项目管理计划组件包括(但不限于)资源管理计划
资源管理计划为 如何管理和最终遣散项目团队资源提供指南
责任分配矩阵,假如团队是由内部和外部人员组成,RACI 矩阵对明确划分角色和期望特别有用
4:项目经理说:我现在不能处理这件事
此时,该项目经理用的何种冲突解决技巧
What conflict resolution technique is a project manager using when he says, I cannot deal with this issue now