福建吴航不锈钢制品有限公司产线调整就地改造项目钢结构工程施工组织设计单位:福建建工集团总公司编制:审核:批准:目录1.编制说明.................................................51.1编制依据...........................................51.2编制原则...........................................51.3本工程采用的主要技术规范...........................52.工程概况及特点...........................................62.1工程概况...........................................62.2施工条件...........................................82.3工程特点...........................................83.项目组织机构.............................................103.1项目部的组成.......................................103.2项目管理体制.......................................113.3项目部高效运作的保证措施...........................133.4项目部的协调管理...................................144.施工部署.................................................154.1工程目标...........................................154.2施工总体安排.......................................155.施工总平面布置...........................................175.1施工总平面布置.....................................175.2施工现场用水用电的确定.............................186.施工进度计划.............................................206.1施工进度安排.......................................206.2保证工期的措施.....................................217.施工准备.................................................227.1技术准备...........................................227.2现场准备...........................................227.3劳动力需用计划.....................................237.4施工机械配备.......................................238.主要施工方法.............................................248.1测量放线...........................................248.2钢构件制作.........................................248.3吊车梁制作方案.....................................338.4钢结构工厂焊接.....................................388.5钢结构除锈、涂装方案...............................458.6钢结构运输.........................................508.7钢结构现场拼装方案.................................519钢结构吊装方案............................................549.1施工机械的选择安排.................................549.2柱子系统施工.......................................549.3柱间支撑的吊装.....................................659.4吊车梁施工工艺.....................................679.5围护系统的安装.....................................739.6油漆工程...........................................7410.保证质量的措施..........................................7510.1质量保证体系......................................7510.2质量保证制度......................................7910.3质量控制措施......................................7910.4质量管理措施......................................8011.安全保证措施............................................8011.1项目安全机构设置..................................8011.2安全控制措施......................................8312.文明施工保证措施........................................8512.1组织机构..........................................8512.2现场管理措施......................................8713.环境保护措施............................................8713.1环境保护管理办法..................................8713.2环境保护措施......................................8814.降低成本的措施.........