威海国际商品交易中心施工组织总设计之二总体暨电气篇第1页共40页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第1页共40页工程名称:威海国际商品交易中心责任人:李刚编制人:卢绪年日期:2005年1月5日一、编制依据··············································3二、工程概况··············································3三、施工组织机构与职责····································41、项目部组织机构示意图···································42、兼职情况说明···········································5第2页共40页第1页共40页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第2页共40页3、职责··················································5四、施工部署··············································71、施工顺序···············································72、施工部署···············································73、工期计划安排···········································84、劳动力组织·············································8五、基础设施和工作环境····································91、设备需用量及劳动力等供应计划···························92、安全用电技术措施·······································103、临时设施施工计划································第3页共40页第2页共40页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第3页共40页·······12六、施工技术措施··········································121、主要分部分项工程施工方法·······························122、治理质量通病措施·······································143、各工种施工配合·········································15七、施工质量保证措施······································161、质量管理目标···········································162、质量保证体系···········································163、以顾客为关注焦点·······································174、文件要求···············································175、人力资源控第4页共40页第3页共40页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第4页共40页制···········································206、采购···················································207、机械设备、周转器材及监视和测量装置·····················208、施工过程控制············································219、产品监视和测量·...