保利琶洲地块四项目火灾自动报警系统综合调试方案编制/时间:年月日审核/时间:年月日审批/时间:年月日【保利琶洲地块四项目火灾自动报警系统综合调试方案】目录1编制依据...................................................................22工程概况...................................................................32.1工程总概况...........................................................32.2系统概况.............................................................43综合调试部署...............................................................83.1项目实施目标.........................................................83.2调试流程及进度计划...................................................83.3调试组织机构.........................................................94准备工作..................................................................134.1消防工程验收前阶段划分..............................................134.2调试前提条件........................................................145安全保证措施..............................................................155.1安全责任制度........................................................155.2三级安全生产教育....................................................155.3安全技术交底........................................................155.4现场安全跟踪督促....................................................155.5通用规定............................................................156调试进度控制管理..........................................................166.1调试流程图:........................................................166.2调试工具仪器准备....................................................176.3调试前准备..........................................................176.4各项调试时间节点及施工资源配置......................................206.5常见故障及处理方法..................................................376.6需配合调试的有关厂家................................................387调试内容及方法............................................................397.1系统调试前准备......................................................397.2自动报警系统调试....................................................397.3消防通信系统调试....................................................427.4消防广播系统调试....................................................427.5防排烟系统的调试(正压送/补风、排烟、排烟百叶/天窗、挡烟垂臂)........437.6非消防电源切断、应急照明及智能疏散系统调试..........................537.7防火卷帘门、自动门、防火门系统调试..................................557.8安防系统(CCTV系统、门禁系统).....................................577.9自动喷淋系统的调试..................................................577.10消火栓系统的调试...................................................617.11水炮系统调试.......................................................637.12气体灭火系统调试...................................................667.13电梯、扶梯自动步道调试.............................................687.14低压配电系统(低压配电箱/柜启动应急照明、低压配电箱/柜停非消防源).687.15动力系统调试(水泵控制柜、风机控制柜).............................707.16全系统综合联动调试.................................................718调试过程中使用表格........................................................749系统验收..................................................................8810验...