贵州省某大桥主桥施工监控实施方案监控单位:某某监控项目部二〇一五年一月目录一技术建议书项目组织机构及人员组成·················································11.1施工监控实施组织及计划·····························································11.1.1施工监控实施组织···················································································11.1.2施工监控计划·························································································11.2项目组织机构及人员组成·····························································4二监控人员、设备安排及进出场计划····················································52.1拟投入本项目的主要人员································································52.2拟投入本项目的仪器······································································52.3拟投入软件··················································································62.4进出场时间安排············································································6三施工监控实施方案·········································································73.1概述··························································································73.2工程特点、难点及对策···································································73.3施工监控目标、原则及方法·····························································8(一)施工监控目标······················································································8(二)施工控制原则······················································································8(三)施工监控方法······················································································93.4施工监控工作内容········································································10(一)仿真计算···························································································10(二)施工监控计算参数的采集········...