富锦油库增容及达标改造项目富锦油库增容及达标改造项目施工组织设计编制人:审核人:批准人;哈尔滨天源石化工程有限责任公司第0页共30页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第0页共30页目录一、工程概况................................................................2二、编制依据................................................................2三、主要工程量..............................................................2四、主要施工步骤............................................................3五、主要施工难点:..........................................................4六、主要施工方法............................................................56.1施工程序.......................................................................56.2、施工配合.....................................................................56.3.电缆沟挖掘....................................................................66.4、电缆保护管的敷设.............................................................66.5、PLC操作台安装................................................................76.6、电缆敷设.....................................................................76.7、仪表开箱检查.................................................................76.8、仪表的安装...................................................................76.9仪表的接线应符合下列规定.......................................................86.10、施工应达到的各项技术质量指标................................................86.11、安装质量通病防治措施........................................................9七、SHE管理组织机构与职责..................................................107.1、项目部HSE组织机构.......................................................................................................................107.2、主要成员的职责..............................................................................................................................107.2.1、HSE管理小组职责...........................................................107.2.2、项目HSE经理职责..........................................................117.2.3、专业工程师职责。..........................................................117.2.4、专业施工队长职责..........................................................117.3、应急预案..........................................................................................................................................127.3.1、本项工程安全控制点:..............................................................................................................12八、施工进度计划及保证措施.................................................138.1、施工进度计划(见附件)..............................................................................................................138.2、施工进度计划控制流程图..............................................................................................................138.3、施工进度控制措施........................................................................................................................138.4、组织措施....................................................................148.5、技术措施...................................................................148.6、材料保证措施................................................................148.7、机械设备保证...