新建铁路银川至西安客运专线吴银段站前IV标银川车站8、9道过渡施工方案编制:李芳复核:武林审核:闫福全中铁二十一局集团有限公司银吴客专项目经理部二〇一六年十一月七日目录1.项目基本情况.........................................11.1施工项目基本情况...............................11.2施工项目及作业内容............................11.3施工单位及负责人...............................21.4施工作业时间.......................................21.5施工地点..............................................21.6施工影响范围.......................................21.7设备变化情况.......................................21.8LKJ数据................................................31.9配合单位..............................................32.技术标准................................................33.运输条件................................................34.施工程序及方案.....................................44.1施工程序..............................................44.2施工方案..............................................44.2.1邻近施工..........................................44.2.2封锁施工..........................................65.施工条件..............................................95.1各专业节点工期安排............................95.2施工机具及材料情况............................95.3LKJ数据:............................................106.劳力组织..............................................107.施工方法及质量保证措施....................118.行车安全措施.......................................228.1施工防护............................................228.2封锁要点现场防护布置......................238.4营业线监测.........................................258.5危险源辨识与控制措施......................259.劳动安全措施.......................................269.1上线作业............................................269.2跨越线路............................................269.3隔离防护............................................279.4高空作业............................................2719.5劳动保护及安全防护用品..................279.6防触电................................................279.7施工大型机械.....................................289.8电气化安全.........................................289.9冬施措施............................................2810.应急预案..............................................2910.1应急指挥组织机构............................2910.2施工主要事故及应急预案启动.........2910.3接触网支柱断裂应急预案................2910.4接触线断线应急预案........................3010.6轨道电路短接应急预案....................3110.7轨道车掉道应急处理措施................3211防汛防洪应急预案...............................3212、附件:..............................................342第0页共51页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第0页共51页银吴客专银川站改第一步施工方案1.项目基本情况1.1施工项目基本情况银川站为横列式站型布置,银吴客专双线从银川车站南咽喉引入,东侧为银川车站高速场维持现状4台7线,西侧既有站台线路拆除后建普速站场3台8线,车站南北咽喉道岔整体改造,动车走形线在北咽喉东侧与高速场连接,新建动车运用所在北端通过高架桥跨包兰线后建至包兰铁路西侧,包兰下行正线从K519+500-K523+600段改建至既有客整所东侧,车站包头端还建工务工区1处,银新专用线、普速场客车整备所、普速机车整备所,银川供电段专线维持不变,改建后银新专用线近期暂接入高速场,夜间利用高速场天窗时间进行取送作业,利用动车走行线转场...