xxxxxxx6#楼、17#楼粘贴锚固岩棉板涂料饰面外保温施工方案编制审核北京xxxx高新技术有限公司2010年11月3日目录1工程概况........................................................41。1工程性质....................................................41.2工程概况.....................................................42编制依据........................................................43施工准备........................................错误!未定义书签。3.1材料准备.....................................................53.2机具准备.....................................................83.3基层准备.....................................................93。4技术准备....................................................94施工工艺流程....................................................105施工工艺说明....................................................115。1施工准备...................................................115。2岩棉板施工作业前提.........................................115。3岩棉板及其配套材料进入现场复检要求:.......................115。4基层墙面处理,墙体基面的尺寸偏差应符合下表:...............115.5吊垂直、套方、弹控制线,做灰饼...............错误!未定义书签。5。6粘贴岩棉板、聚苯颗粒找平...................................125.7抗裂砂浆层施工..............................................136质量验收.......................................................146.1保温工程验收资料准备........................................146.2保温工程检验批..............................................146。3质量验收...................................................147质量保证措施....................................................157.1质量承诺服务措施...........................................157.2质量检查....................................................157.3严把六关....................................................157。4技术资料...................................................157.5质量控制要点................................................167.6质量控制管理体系............................................168工期保证措施....................................................169安全施工保证措施................................................179。1总包方的安全管理措施.......................................179。2安全施工措施...............................................179.3临电管理制度................................................199。4安全生产技术组织措施.......................................199.5防火组织措施................................................209.6电气设备防火措施............................................209.7确保安全技术措施............................................2010文明施工措施...................................................2110.1文明施工...................................................2110.2环境保护管理...............................................2210。3环境卫生管理..............................................2311材料管理及节约措施.............................................2312环保管理及消防防火措施.........................................2313成品保护措施...................................................242/2514施工技术资料管理...............................................2415技术节约措施...................................................253/251工程概况1.1工程性质1.1.1工程名称:南京xxxx外滩新城二期B地块-住宅6#楼、17#楼1。1。2建设单位:南京xxxx房地产开发有限公司1。2工程概况本工程...