目录第一章工程概况....................................................................................................................1第二章施工部署....................................................................................................................1第三章施工工艺及技术措施................................................................................................2一、施工工艺....................................................................................................................2(一)立柱桩施工......................................................................................................2(二)立柱桩格构柱制作与安装..............................................................................3(三)混凝土浇筑....................................................................................................4(四)空孔回填............................................................................................................5二、施工保证措施............................................................................................................5(一)立柱桩入岩要求:....................................................................................................5(二)格构柱定位、固定与吊装....................................................................................5第四章施工进度....................................................................................................................7一、施工进度计划............................................................................................................7二、工期保证措施............................................................................................................7第五章施工质量保证措施..................................................................................................10第六章安全、消防施工保证措施........................................................................................11一、消防及用电安全......................................................................................................11二、格构柱加工、吊装过程中的安全措施..................................................................11三、格构柱施工安全措施..............................................................................................11四、管线保护安全措施..................................................................................................11第七章成品保护....................................................................................................................12第一章工程概况第二章施工部署一、生产准备:(一)、人员准备:根据施工作业计划,安排施工人员.施工人数由作业队根据工程部统一安排,按南北分为两个作业队,劳动力安排如下表2-1:工种管理人员钻机队司机(挖、吊)砼工(成桩)钢筋工(成笼)电焊工(成笼)电工人数进场时间表2—1劳动力安排表(二)、施工机具及材料进场准备;1、施工机具:为保证施工要求,我项目部计划在立柱施工过程中投入以下机械设备,如2—2表所示:表2-2施工机械设备表序号123456782、施工材料:桩身混凝土:采用商品混凝土,强度等级为C30。1退场时间备注施工现场机械名称冲击钻钢筋切割机钢筋切断机电焊机弯曲机套丝机吊车挖掘机台数102282222准备钢筋:钢筋的品种、级别、规格必须符合设计要求,有产品合格证,表面清洁无老锈和油污.并按要求进行取样做机械性能试验,合格后方可使用。格构柱:格构柱角钢强度为Q345,缀板强度为Q235。二、技术准备:1、根据地...