深圳市地铁龙岗线工程建设项目管理咨询及设计监理服务Shenzhen Metro No. 3 LineProject Management Consultancy& Design Supervision安装装修策划报告A28/10/2008初稿陈志立CCL王 宏MWH向恒飞HFX谭伟强BT版本Rev.日期Date修订描述Description of Amendments编写Prepared复核Checked审查Reviewed批准Approved提交文件编号Submission No.SZM3-PMDS-SMCO-A000000-PC210-08/000078版本Rev.A目录1. 前言.......................................................................................................22. 车站安装装修的范围及接口...............................................................2 2.1 土建标段的范围...........................................................................2 2.2 系统承包商的范围.......................................................................3 2.3 公共区装修承包商的范围...........................................................43. 安装装修的实施计划...........................................................................4 3.1 进场时间.......................................................................................6 3.2 信号、通信设备房的进场要求...................................................7 3.3 大型设备运输的安排...................................................................84. 各设备房的装修工作内容...................................................................95. 设备安装、装修工序安排.................................................................146. 现场管理.............................................................................................157. 其他现场管理办法的编写.................................................................211. 前言2008 年是深圳地铁龙岗线工程“土建施工及设备生产年”,各车站土建主体结构将在今年底至明年初陆续完成,紧随而来的设备安装、装修将在年底及明年第一季度进场,从而将形成有各种不同专业队伍在同一时间, 同一区域内“混合大干”的局面。由于土建进度较原计划滞后严重,部分车站主体结构要到 2009 年 1~3 月才能完成,距开通目标只有 19 个月时间。要保证 2010 年 10 月底按期...