软基处理现场监理实施细则目 录第一章 软土地基处治施工规范要求,施工图设计要求及评定标准·······109第二章 工程质量监控管理程序····················································119第一节 工程质量控制流程·······················································119第二节 现场质量控制·····························································121第三节 对承包人管理人员的要求··············································124第三章 分项工程质量监理程序····················································125第一节 清表施工监理程序·······················································125第二节 砂垫层施工监理程序····················································127第三节 袋装砂井施工监理程序·················································129第四节 粉喷桩施工监理程序····················································132第四章 填报表格······································································137第一章 软土地基处理施工规范要求、施工图设计要求及评定标准1 一般规定1