山西晋城高硫煤洁净利用化电热一体化示范工程主体工程安装1 标段2×240t/h 循环流化床锅炉安装方案批准:审核:编制:河南省安装集团有限责任公司二○一五年四月目录第一章概述······································1第二章锅炉钢架组合吊装 ··························4第三章空气预热器安装 ····························9第四章水冷壁安装 ································11第五章省煤器安装 ································13第六章过热器安装 ································14第七章锅筒及下降管 ······························15第八章旋风分离器安装 ····························16第九章汽水连接管及其它管道安装··················17第十章锅炉水压实验 ·····························18第十一章锅炉化学清洗 ·····························22第十二章质量保证措施 ·····························26第十三章安全生产、文明施工措施···················30附 1 劳动力安排 ···································34附 2 主要施工机具安排 ·····························35附 3 本工程需用规程、规范、标准···················46附 4 钢架排架拼装示意图 ···························47附 5 塔吊布置位置示意图 ·