隧道浅埋岩堆体108ø大管棚超前支护施工工艺编制: 审核:彭酉项目经理部二 00 三年十一月三十日目 录下载后可任意编辑1.前言·····································22.工程概况·································22.1概述··································22.2大管棚变更情况························32.3大管棚超前支护方法····················43.施工工艺·································73.1测量放样······························73.2钻孔························1下载后可任意编辑··········93.3配管·································113.4送管·································123.5下钢筋笼·····························133.6管口封闭·····························133.7注浆·································133.8沉降观测·····························183.9事故预防和处理·······················182下载后可任意编辑3.10机具设备和劳力······················194.安全措施································205.结论····································216.相关知识点······························217.主要参考书目····························241.前言重庆市彭(水)酉(阳)二级公路 A 标段下南城隧道全长 772m(K2+423~K3+195),但其进口处于破裂土岩堆地段长达 182m(K2+423~K2+605),且最浅埋深仅 2m,同时围岩含水量大,工程力学性质差,开挖后易坍塌,成洞困难。为确保开挖稳定,进口 K2+433~K2+488 段 55 m,隧道拱部 120°范围采纳 ø108×8mm 超前大管棚注浆支护辅助施3下载后可任意编辑工,共设两环,每环钢管总长度 30m。我公司施工类似大直径的长...