下载后可任意编辑目 录一、工程概况...................................................1二、主要工程数量表.............................................1三、总体施工方案具体实施步骤...................................1四、主要施工工艺及施工方法.....................................2五、施工人员及施工设备安排.....................................5六、工期安排...................................................6七、霸王河内墩身施工完成后纵向贯穿便道过渡方案.................6八、现场管理机构、职责分工.....................................6九、雨季及汛期施工措施.........................................7十、便道筑岛土方及钻孔泥浆的清理...............................7十一、安全保证措施.............................................8十二、应急预案.................................................912.1 应急准备.........................................................912.2 人员准备.........................................................912.3 物资准备.........................................................1112.4 应急响应........................................................1212.5 外援救助.........................................................1212.6 事后工作.........................................................1312.7 应急预案的纠正与完善............................................1312.8 保证措施.........................................................13十三、质量保证措施............................................1513.1 一般性质量保证措施...............................................1513.2 工程质量保证措施.................................................17十四、工期保证措施............................................2014.1 确保工期的组织措施...............................................2014.2 保证工期的制度措施...............................................2414.3 保证工期的技术措施...............................................2614.4 特别时段工期保证措施.............................................2914.5 确保工期的应急措施........................................