摘 要深基坑支护属临时性工程,支护目的是为下道工序制造施工条件
随着我国房地产业进展的需要以及城市规划用地资源的紧缺,深基坑工程越来越多,但因深基坑支护属临时性工程,往往被施工单位所忽略,施工事故急剧上升,造成巨大的经济损失
加强深基坑支护施工工艺及质量控制是关键,有效减少施工事故,控制修建成本为目的,所以对深基坑支护施工工艺及质量控制的讨论具有重要的应用价值
关键词:深基坑支护;施工工艺;质量控制
AbstractDeep foundation pit bracing project is belong to temporary work
The purpose of bracing is to creat the conditions of construction for the next working procedure
There are more and more deep foundation pit projects with the developing demands of the realty industry and the lack of land resources for urban planning
However, they are often ignored by construction units for which are belong to temporary work
Therefore, construction accidents rised sharply, and it made huge economic loss
The key is to enhance the construction technology and the controlling of qulality of deep founda