***项目外保温及涂料施工方案 ***公司2013 年 5 月 28 日目 录一.编制依据......................................................3二.工程概况......................................................3三.施工准备......................................................43.1 材料组成及要求.............................................43.2 机具准备...................................................63.3 人员准备及计划安排.........................................83.4 技术准备...................................................8四.施工条件......................................................9五.工艺流程......................................................95.1 基层处理..................................................105.2 测量、放线、挂基准线......................................105.3 配制聚合物粘结砂浆........................................105.4 预粘贴板边翻包网格布......................................115.5 粘贴聚苯板及岩棉板........................................115.6 保温板打磨、找平,涨栓辅助加固............................155.7 滴水槽或鹰嘴..............................................165.8 抹第一遍面层聚合物抗裂砂浆................................165.9 埋贴网格布................................................165.10 抹面层聚合物抗裂砂浆.....................................185.11 EPS 线脚安装.............................................195.12 门窗侧口保温板做法.......................................195.13 其他节点做法详图.........................................195.14 涂料施工…………………………………………………………………20六.应注意的质量问题...........................................204七.工程验收....................................................255八.安全措施....................................................2778.1 吊篮施工安全要求.........................................2778.2 吊篮平台的要求...........................................2778.3 提升机构的要求...........................................2888.4 安全保护装置的要求.................