目 录一、编制依据.......................................................................................2二、试桩准备工作................................................................................21、试桩地点..................................................................................22、试桩地点地质情况......................................................................23、试桩材料..................................................................................2三、施工准备.......................................................................................31、场地平整..................................................................................32、机械组装与调试.........................................................................33、水泥进场保存............................................................................44、测量放样..................................................................................4四、施工工艺方法................................................................................41、水泥浆制备...............................................................................42、钻机就位..................................................................................43、喷浆钻进..................................................................................44、喷浆搅拌提升............................................................................55、复搅、复喷...............................................................................56、移位.........................................................................................57、施工参数..................................................................................5五、质量控制方法及手段.......................................................................6六、成桩检测.......................................................................................6七、试桩结果总结................................................................................7...