齐齐哈尔中汇城乐鹤公元地块项目外墙保温工程施工方案编制单位:天津胜茂建筑工程集团有限公司编制时间:2025 年 6 月 22 日目 录一、编制依据.............................................................................3二、工程概况.............................................................................4三、施工部署.............................................................................43.1 施工安排..........................................................................43.2 施工进度计划安排..................................................................33.3 劳动力组织安排....................................................................43.4 质量控制保证体系..................................................................43.5 样板施工..........................................................................53.6 技术先行..........................................................................5四、施工方案.............................................................................51、施工准备..........................................................................52、施工工艺流程.....................................................................123、作业条件.........................................................................134、施工工艺.........................................................................135、施工要点.........................................................................21五、质量保证措施........................................................................22六、进度保证体系........................................................................26七、安全保证体系........................................................................26八、成品、半成品保护措施................................................................28九、文明施工措施........................................................................28十、消防安全措施........................................................................29十一、季节性...