李阳河渠道倒虹吸进口渐变段挡土墙地基处理方案李阳河渠道倒虹吸进口渐变段挡土墙地基处理方案 摘要:南水北调中线一期工程总干渠李阳河渠道倒虹吸进口渐变段挡墙采纳 CFG 桩进行地基处理。施工工序包括:地表处理、桩位测量放样、钻机就位、钻孔、砼运输与泵送、钻机移位、桩头处理、检测、施工质量控制等。CFG 桩施工以改善地基不均匀沉降、提高地基承载力为目的。其中,选择合理的施工机械,确定合理的施工参数,是对施工质量及施工进度、施工成本控制的关键。 关键字:倒虹吸;地基处理;方案 Abstract:Middle route of South-to-North Water Transfer Project Li Yanghe channel inverted siphon inlet transition pipe retaining wall using CFG pile for foundation treatment. The construction process includes: surface treatment, pile spacing measurement lofting, drilling emplacement, drilling, concrete transportation and pumping, drill displacement, pile head, detection, quality control of construction. CFG pile construction to improve the uneven settlement of foundation, improve the bearing capacity of the foundation for the purpose of. Among them, reasonable selection of construction machinery, determine the reasonable construction parameters, the construction quality and construction progress, construction cost control key.Key words: inverted siphon;foundation treatment;Scheme. 中图分类号:TU444 文献标识码:A 文章编号:2095-2104(2025) 1、引言 地基处理是一般是指用于改善支承建筑物的地基(土或岩石)的承载能力或抗渗能力所实行的工程技术措施。地基处理工程的设计和施工质量直接关系到建筑物的安全,如处理不当,往往发生工程事故,且事后补救大多比较困难。因此,对地基处理要求实行严格的质量控制和验收制度,以确保工程质量。 2、工程概况 李阳河渠道倒虹吸位于内邱县城西南双流村东的李阳河两支流交汇口下游 80m 处。倒虹吸设计流量 220m3/s,加大流量 240m3/s。 施工开挖后发现挡墙地基土层不均匀,基础分部有中砂、壤土、粘土与粗砂,且粗砂占很少部分,变化明显,承载力偏低,设计选用水泥粉煤灰碎石桩(CFG 桩)对挡墙地基进行处理。...