鄯善县地湖煤矿主、副斜井井筒掘进工程施工组织设计鄯善县地湖煤矿二0一三年十一月七日目录第一章编制依据和编制原则...............................1第二章工程概况.................................................................2第一节矿井简介.......................................................2一、交通位置..........................................................2二、地形地貌..........................................................2三、水系........................................................................3四、气象........................................................................3五、地震烈度..........................................................3六、井田经济概况.............................................3七、矿井开拓设计方案...............................3第二节水文及地质特征..................................4一、水文特征..........................................................4二、工程地质情况.......................................................7三、工程概况.....................................................................8第三章施工准备..........................................................11第一节技术准备..............................................................11第二节施工人员进场......................................11第三节工程准备...................................................12第四节井筒施工准备......................................14第五节施工队伍安排......................................14第四章施工方案及凿井系统设置.............14第一节表土段施工.............................................14一、施工方案.......................................................14二、表土段施工................................................15第二节基岩段施工.............................................19一、主、副斜井施工方案....................19二、施工方法.......................................................20第五章施工辅助系统设置..................................27第一节提升系统及设备选型.................27第二节、压风系统...................................................29第三节、通风系统...................................................29第四节、排水、供水系统...............................32第五节、供电系统...................................................32第六节、照明、通讯与信号........................32第七节、地面临时设施......................................33第八节、设备、材料供应计划.................35第六章施工组织措施.............................................35第一节、施工组织机构和劳动力配备...35第二节、正规循环作业......................................35第七章工期进度安排及保证措施.............40第一节施工进度计划......................................40第二节施工排队图(后附).................40第三节工期保证措施......................................40第八章工程质量目标及保证措施.............41第一节工程质量目标......................................41第二节工程质量标准......................................41第三节质量保证体系......................................41第四节质量保证措施......................................41第九章安全专项管理与措施...........................47第一节安全目标...................................................47第二节安全管理机构......................................47第三节安全检查、控制措施.................50第四节安全教育培训......................................51第五节预控防范措施...........