五里河大厦工程施工组织设计金帝二建五里河大厦项目经理部二○○三年五月二十日目录1.工程概况.....................................................................................................31.1.工程地点.................................................................................................31.2.建筑概况.................................................................................................31.3.相关数据.................................................................................................31.4.编制依据.................................................................................................32.目标.............................................................................................................32.1.质量目标.................................................................................................32.2.工期目标.................................................................................................42.3.安全、文明施工目标.............................................................................43.工作内容分解.............................................................................................44.特点、质量控制要点.................................................................................44.1.特点分析.................................................................................................44.2.质量控制要点.........................................................................................55.职责表.........................................................................................................55.1.组织机构图.............................................................................................55.2.项目部人员职责表.................................................................................66.资源配置.....................................................................................................86.1.施工总体部署.........................................................................................86.2.主要施工机械设备表...........................................................................106.3.劳动力自然情况及计划表....................................................................116.4.临时设施布置及临时用地表...............................................................127.网络图、甘特图计划...............................................................................127.1.施工进度计划甘特图...........................................................................127.2.施工进度计划网络图...........................................................................128.重点项目专项方案...................................................................................138.1.土建主要分部分项工程施工方法.......................................................138.2.电气工程分部分项工程施工方法.......................................................428.3.水暖工程分部分项工程施工方法.......................................................549.施工总承包管理措施...............................................................................679.1.总体措施...............................................................................................679.2.分包单位进场准备管理要点...............................................................689.3.施工过程的技术管理要点...........