某高速公路第5合同段(K20+800~K20+935)左侧滑坡处治施工组织设计xx路桥工程有限公司xx年xx月xx日目录1工程概况·······································································································11.1地形地貌·································································································11.2地层岩性·································································································11.3水文地质特征·························································································12施工组织方案·································································································12.1施工方案·································································································12.2施工程序·································································································12.3施工监测要求及应急措施·····································································63施工场地布置·································································································63.1临建·········································································································63.2拌和站·····································································································63.3施工临时用电·························································································63.4施工临时用水·························································································73.5施工临时道路·························································································74施工总体部署·······························································································74.1劳动力组织计划·····················································································74.2主要材料供应计...