第0页共95页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第0页共95页重庆85万吨/年甲醇装置挡土墙工程施工组织设计编制日期:二00九年二月第1页共95页第0页共95页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第1页共95页目录一、编制说明········································二、编制依据及原则··································2.1编制依据·····································2.2编制原则·····································三、工程管理目标·····································第2页共95页第1页共95页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第2页共95页四、工程概况·········································4.1工程地理位置·································4.2施工场地周围环境·····························4.3工程地质·····································4.4工程范围及规模·······························第3页共95页第2页共95页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第3页共95页4.5工程主要特点·································五、设备、人员动员周期及材料组织供应··················5.1人员、设备动员周期····························5.2技术准备······································5.3材料组织供应··································六、施工准备及临时设施····························第4页共95页第3页共95页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第4页共95页···6.1临时房屋设施··································6.2水、电设施····································七、施工组织机构的建立·······························7.1组织机构设置·································7.2施工组织管理机构的运作························八、施工计划····························第5页共95页第4页共95页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第5页共95页··············8.1工期进度计划·································8.2各施工队伍人员构成···························8.3施工设备计划·································8.4材料供应计划及措施···························九、施工方法··········································9.1挡土墙构造····································9.2填土施工要求··································9.3锚杆挡土墙施工································第6页共95页第5页共95页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第6页共95页9.4施工工艺流程··································9.5扶壁式挡土墙施工·...