鸭池河水电站土建工程(合同编号:TY-YCH-001)鸭池河水电站坝后背管段分部工程施工组织措施编写:审核:批准:水电九局鸭池河水电站项目部2004年12月目录第一章工程概况..........................................................................................................................11.1工程简述...........................................................................................................................1第二章施工布置..........................................................................................................................12.1施工用水.............................................................................................................................12.2施工用电.............................................................................................................................12.3施工通讯.............................................................................................................................1第三章施工方案..........................................................................................................................23.1浇筑安排.............................................................................................................................23.2仓面清理.............................................................................................................................23.3测量放样.............................................................................................................................23.4钢筋制安.............................................................................................................................33.5立模和支撑.........................................................................................................................33.6混凝土拌制及运输.............................................................................................................33.7混凝土入仓浇筑.................................................................................................................33.8混凝土的平仓及振捣.........................................................................................................43.9混凝土养护.........................................................................................................................53.10进料口及溜筒的布置顺序...............................................................................................53.11坝后背管段分部工程施工流程图...................................................................................7第四章劳动力人员安排、机械设备配置及施工进度计划.......................................................84.1劳动力人员安排................................................................................................................84.2机械设备配置...................................................................................................................94.3施工进度计划...................................................................................................................9第五章质量、安全保证措施.....................................................................................................105.1施工质量保证措施..........................................................................................................105.1.1质量保证体系.........................