成都理工大学毕业设计(论文)靖远煤业集团公司职工文体活动中心施工组织设计作者姓名:李文杰学号:200703010428专业:土木工程(建筑方向)指导教师:周舒【摘要】本施工组织设计是针对靖远煤业集团公司职工文体活动中心工程设计方案实施性文件。编制时对项目管理机构设置、施工总体部署、施工准备、主要部分分项工程施工方法、工程质量保证措施、安全及文明施工措施、施工现场管理措施等诸多因素尽可能充分考虑,突出科学性、实用性及针对性,是确保优质、低耗、安全、文明、高速完成全部施工任务的重要经济技术文件。本设计主要包括以下内容:工程施工组织设计书、施工平面布置图、横道图及网络图。为确保工期、质量及安全、文明工地、节约成本等条件,编制出针对性的施工组织设计,每个分项工程的特点、结构特征、施工难易程度、工期和质量要求,编制出切实可行的施工方案。以指导施工顺利地完成本工程项目的建设,控制工程成本,创建优质工程。【关键词】工程概况;平面布置及管理;施工进度计划;施工方案成都理工大学毕业设计(论文)2成都理工大学毕业设计(论文)JingyuancoalgroupcompanyworkertherecreationalactivitycentertheconstructionorganizationdesignName:LiWenJieStudentNo.:200703010428Major:Civilengineering(architecturedirection)Supervisor:ZhouShuAbstract:Theconstructionorganizationdesignisaimedatjingyuancoalgroupcompanyworkertherecreationalactivitycenterprojectdesignplanimplementationsexfiles.Prepareforprojectmanagementinstitutionswhensetting,constructionoverallarrangement,constructionpreparation,mainpartcomponentprojectconstructionmethod,engineeringqualityassurancemeasures,safetyandcivilizedconstructionmeasures,constructionsitemanagementmeasures,andmanyotherfactorstoconsiderasfullyaspossible,outstandingscientific,practicalandpertinence,istoensurehigh-quality,lowconsumption,safety,civilization,high-speedfinishalltheimportanttaskofeconomicconstructiontechnicaldocuments.Thisdesignincludesthefollowingcontent:engineeringconstructionorganizationandarchitecture,constructionlayout,abarchartandnetworkdiagram.Toensurethequalityandsafetyperiod,thecostsavings,civilizedconstructionsite,formulatespecificconditionssuchastheconstructionorganizationdesign,thecharacteristicsofeachcomponentprojectconstruction,structurefeaturesanddegreeofdifficulty,scheduleandqualityrequirements,formulatefeasibleconstructionscheme.InordertoguidetheconstructionsuccessfulcompletionofthisprojectKeywords:Engineeringoutline;Layoutandmanagement;Constructionschedule;Constructionscheme3成都理工大学毕业设计(论文)4JingyuancoalgroupcompanyworkertherecreationalactivitycentertheconstructionorganizationdesignName:LiWenJieStudentNo.:200703010428Major:Civilengineering(architecturedirection)Supervisor:ZhouShuAbstract:Theconstructionorganizationdesignisaimedatjingyuancoalgroupcompanyworkertherecreationalactivitycenterprojectdesignplanimplementationsexfiles.Prepareforprojectmanagementinstitutionswhensetting,constructionoverallarrangement,constructionpreparation,mainpartcomponentprojectconstructionmethod,engineeringqualityassurancemeasures,safetyandcivilizedconstructionmeasures,constructionsitemanagementmeasures,andmanyotherfactorstoconsiderasfullyaspossible,outstandingscientific,practicalandpertinence,istoensurehigh-quality,lowconsumption,safety,civilization,high-speedfinishalltheimportanttaskofeconomicconstructiontechnicaldocuments.Thisdesignincludesthefollowingcontent:engineeringconstructionorganizationandarchitecture,constructionlayout,abarchartandnetworkdiagram.Toensurethequalityandsa...