目录1、工程概况···············································································22、施工准备···············································································33、主要分部分项工程施工方法·····················································104、厂区设施施工·······································································315、施工总进度计划及措施···························································346、质量保证措施·······································································377、安全生产措施、环境保护、文明施工措施···································498、安全生产管理、费用及责任人员落实情况···································601、工程概况1
1工程概况工程项目组成:1
2施工技术难点及处理措施1、砼浇筑:体积小、断面小,易出质量问题
严格从半成材料开始控制,认真按工艺流程作业,从立模→拌合→运输→浇筑→捣实→收面→养护,每一道工序严格控制
2、集水池工程:部分施工用材料需采用人工二次转运,我单位将采用拓宽人行路面,尽可能采用小型拖拉机结合胶轮车运输
3、附属设施工程:本工程主要为水处理厂工程,还涉及办公楼入厂公路等,组成项目较多