保利番禺汉溪项目场地平整及土石方工程施工组织设计目录1、工程概述..............................................................31.1工程概况..............................................................31.2工程重难点分析和解决措施..............................................52、项目组织机构..........................................................72.1项目管理机构..........................................................72.2项目管理部门职责......................................................83、施工方案.............................................................103.1施工放线测量.........................................................103.2土方开挖施工.........................................................103.3石方爆破施工.........................................................163.4土方填筑施工方案.....................................................363.5土方调配方案.........................................................444、工期安排及进度保证措施...............................................464.1施工进度计划安排.....................................................464.2工期保证措施.........................................................475、施工平面布置.........................................................525.1施工平面布置说明.....................................................525.2施工现场平面管理.....................................................546、劳动力投入计划.......................................................556.1劳动力投入计划.......................................................556.2劳动力保证措施.......................................................567、施工机械投入计划.....................................................577.1机械设备投入计划.....................................................577.2机械设备投入计划.....................................................598、质量保证措施.........................................................618.1质量管理目标.........................................................618.2质量验收标准.........................................................618.3质量保证体系.........................................................628.4质量控制措施和管理办法...............................................649、安全保证措施.........................................................719.1安全生产目标.........................................................711保利番禺汉溪项目场地平整及土石方工程施工组织设计9.2安全保证体系.........................................................719.3安全保证措施.........................................................7510、文明施工措施........................................................8010.1文明施工目标........................................................8010.2文明保证体系........................................................8010.3文明施工措施........................................................8111、环境保护措施........................................................8511.1废气处理............................................................8511.2废水处理............................................................8611.3噪声防护............................................................8611.4人群健康保护........................................................8611.5废弃物处理..........................................................8711.6工地保洁......................................