SNS主动防护网施工技术方案2————————————————————————————————作者:————————————————————————————————日期:福永街道2016年地质灾害治理工程-白石厦社区昌荣有限电机厂南山体边坡工程主动防护网施工方案编制人:审核人:审批人:编制单位:化工部郑州地质工程勘察院审批日期:二O一七年七月二十日福永街道2016年地质灾害治理工程-白石厦社区昌荣有限电机厂南山体边坡主动防护网施工方案目录一、工程概况····················································································3二、编制依据····················································································3三、工程措施····················································································4四、施工工艺····················································································4五、施工方法····················································································71、测量放线···········································································72、人工清理坡面浮土及浮石、搭设施工脚手架······························73、测量放线确定锚杆孔、钻孔并清孔··········································74、安装锚杆并注浆··································································77、铺设高强度钢绳菱形网并缝合················································88、预应力加固·······································································8六、施工进度安排··············································································8七、资源配置····················································································81、劳动力配置········································································82、主要施工机械设备配置·························································83、主要材料供应·····································································9八、交通安全、保通措施·····································································9九、质量保证措施············································································10十、安全生产措施················...