麻城湖广移民公园建设工程寻根问祖轴施工组织设计****景观工程有限公司麻城湖广移民公园项目部二零一三年九月目录一、工程概况·······································01二、编制说明·······································01三、施工方案、主要部位·····························01四、冬雨季施工技术措施·····························12五、质量保证措施及质量保证体系图···················12六、工期保证技术措施·······························16七、安全技术措施···································18八、现场文明施工管理措施···························19九、环保措施·······································20十、消防措施·······································21十一、节能措施·····································21十二、赶工措施·····································22十三、附件:········································23附一、施工总平面布置图附二、工程综合施工网络进度计划图附三、技术劳力要求表附四、主要施工机械、机具安排表附五、组织机构图附六、安全保证体系图一、工程概况本工程为麻城湖广移民文化公园工程之寻根问祖轴,位于麻城市麻城湖广移民文化公园内,由麻城湖广移民文化公园建设开发有限公司招标筹建,****景观工程有限公司中标承建
工期为365天,要求