1龙德·四季新城一期水平防护棚施工方案重庆龙德建筑工程有限公司2010.10.102目录编制依据········································································1一、工程概况··································································1二、防护架设计及计算······················································22.1、防护架设计·······························································22.2、防护架计算·······························································2三、防护架搭设方法及技术措施··········································43.1、防护架的搭设方法······················································43.2、防护架搭设的技术措施················································5四、防护架搭设的安全措施················································53水平防护棚施工方案编制依据1、龙德·四季新城一期1、8幢工程设计施工图。2、有关工具性参考资料,如:工程定额、类似工程的建设资料、估算指标、建筑施工手册等。3、建设单位施工总平面规划、本工程现场平面布置情况及周边建筑、道路布置情况。4、根据我公司现有技术力量、机械设备能力及以往的施工经验等。5、依据国家现行技术标准、施工及验收规范、工程质量评定标准及操作规程编制而成。主要采用的规范如下:《建筑施工安全检查标准》JGJ59-99《钢结构设计规范》GBJ17-88《重庆市建筑工地文明施工标准》渝建发[2000]39号《建筑施工扣件式钢管脚手架安全技术规程》JGJ130-2001《安装施工工艺操作规程架子工程》DB51/T325-91《建筑施工高处作业安全技术规范》JGJ80-91一、工程概况本工程为龙德·四季新城一期1、8幢工程,位于北部新区礼嘉镇。建筑面积:1#楼14419.38m2,8#楼139909.39m2;建筑高度:地上二十八层,结构总高度93m。由于该建筑紧邻主公路,并且高度较高,拟在每栋楼每13层设一道水平防护棚。每个防护棚面积约800m2。二、防护架设计及计算2.1、防护架设计根据本工程的结构特点和建筑造型,以及周边建筑物和道路的布置情况,在每栋楼立面外侧搭设悬挑水平安全防护架,悬挑长度4m。本工程水平安全防护架采用Φ48×3.5扣件式钢管搭设,13#钢丝绳斜拉。42.2、防护架计算2.2.1、杆件计算悬挑式水平安全防护架采用Φ48×35钢管作为次梁和主梁,上铺竹跳板,主次梁连接采用钢管扣件。2.2.1.1、次梁计算次梁恒荷载(永久荷载)中的自重,钢管以40N/m计,铺板以220N/m2计,活荷载(可变荷载)以1500N/m2计,按次梁承受均布荷载考虑,依下式计算弯矩:mNqlM?6.1342.74146.48081)1(81222222次梁弯曲强度按下式计算:mNfWMn?8.4973.9808.56.1342.2.1.2、主梁计算按外侧主梁以钢丝绳吊点作支承点计算。为安全计,里侧钢丝绳不起作用,5里侧钢管亦不起作用。将次梁传递的恒荷载和活荷载,加上主梁自重的恒荷载,按下列二式计算外侧主梁弯矩值:NqlR4.17252.7615.29.48021121222外mNqlM?04.2611.14.1725818122主梁弯曲强度按下式计算:mNfWMn?2.109221508.504.2612.2.1.3、钢丝绳计算为安全计,水平防护架侧的钢丝绳均以一道钢丝绳受力作计算。钢丝绳所受拉力按下式计算:NqlT8.59045sin21.14.759sin2以钢丝绳所受拉力验算钢丝绳的安全系数K,见下式:107.28.5901570KTFK2.2.2、结构构造计算本水平防护架采用Φ48×3.5钢管作主次梁,主梁悬挑4m。次梁水平间距1.0m,次梁亦采用Φ48×3.5钢管(四根),第一根距里...