公用工程中山市岐江河水环境综合整治工程(雨污分流)某某片区市政污水管工程安全文明施工专项方案编制:审核:审批:编制单位:中山公用工程有限公司编制日期:2013年7月20日目录一、工程概况······························································1二、施工工艺及方法···················21.钢板桩施工的一般要求······························································22.钢板桩施工的顺序····································································23.钢板桩的检验、吊装、堆放·······················································24.钢板桩施打·············································································35.挖土··············································································56.钢板桩的拔除·········································································67.钢板桩土孔处理·······································································6三、安全施工措施····················7四、拉森扣板桩受力验算·················91.