目 录1 概 述..............................................11.1 工程概况.................................................11 编制依据····················································32 施工组织机构.......................................52.1 施工布署原则............................................52.2 现场组织机构配置........................................62.3 施工管理体系............................................6 2.4 公司对安装项目经理部的支持与指导························6 2.5工程施工目标············································133 施工方案..........................................153.1 给水排水管道安装........................................164 安装质量控制措施..................................224.1 工程质量控制目标........................................224.2 工程质量控制体系........................................224.3 工程质量保证措施......................................254.4 推行国际标准加强质量控制..............................264 关键工序的质量控制措施......................................275 施工布置···········································285.1 施工用水、用电计划......................................305.2 施工临时设施计划........................................356 工程进度计划·······································376.1 施工工期目标............................................376.2 施工工期组织原则........................................376.3 工期保证措施............................................387 劳动力安排与计划..................................407.1 劳动力投入计划..........................................407.2 劳动力调配原则..........................................408 施工机械的配备....................................418.1 机械设备的配置或选择....................................418.2 机械设备和...