发包方: (甲方 ) Employer ( party A ) 承包方:(乙方) Contractor ( party B ) 甲乙双方根据《中华人民共和国合同法》和《建筑安装工程承包合同条例》的规定以及建筑工程的具体情况,就乙方承包甲方水暖电和中央通风系统安装项目施工事宜,双方协商一致,签订本合同。Parties hereto, in accordance with LAW OF CONTRACT, REGULATION OF CONTRACTING WITH CONSTRUCTION INSTALLATION and particular case, have made mutual agreement on the issues of party B ‘ s contracting the projects, from party A, of water, electricity and central ventilation system and enter into this contract. 第一条:工程概况 Article One Overview 1、工程名称:水暖电安装工程、中央通风系统安装工程 Project Name : water, electricity and central ventilation system 2、工程地点: Project Place: 3、工程内容及承包范围:Project Contents and Contracting Scope: (一)、电气工程(强、弱电):Electricity Engineering ( Strong and Weak Current ) 1、照明系统:管路预留、预埋、穿线,灯具、插座、开关、配电箱、电度表箱安装及调试等施工图纸要求内容。Lighting system: The contents which are stipulated in drawings comprise the installations and commissioning of pipe presetting, pipe embedded, pipe threading, lamps, sockets, switches, distribution boxes and the like. 2、动力电系统:管路及套管预留、预埋,电缆桥架安装,线缆敷设,配电设备安装及调试等施工图纸要求内容。Electric Power System: The contents required in drawings of pipe and sleeve presetting, embedded, cable tray installation, cable laying, installation and commissioning of distribution and others. 3、弱电系统 : 电视、电话、宽带网、监控:管路预留、预埋(含穿墙套管)及管路清扫等弱电施工图纸要求内容。Weak System: The contents which are stipulated in the drawings of weak power for ( TV, telephone, broadband and monitoring); pipeline presetting, embedded ( include wall bushing) and pipe cleaning and so on. 4、防...