1 JZ L B15 变电站工程质量评估报告 连城新泉 110kV 变电站工程 质 量 评 估 报 告 福建闽能咨询有限公司 (加盖监理公司公章) 2 0 2 0 年 2 月 2 批准: 年 月 日 审核: 年 月 日 编写: 陈文方 2020 年 02 月24 日 3 目 次 1 工程概况 ······················································································· 1 2 质量评估范围 ················································································· 5 3 质量评估依据 ················································································· 5 4 施工过程质量控制综述 ····································································· 6 5 工程质量监理控制概述 ····································································· 7 6 检验批、分项、分部工程和单位工程质量核查情况 ································ 9 7 工程质量评估结论 ········································································· 10 4 连城新泉110kV 变电站工程 质量评估报告 一、工程概况: 1、工程规模: 连城110kV 新泉变电站位于连城县新泉镇新泉村,工程建设规模:1、主变规模 远景3×40MVA,本期 1×40MVA。 2、出线规模及接入系统方案 110kV:远景3 回,分别为 22020 塘厦变、庙前变、朋口变各 1 回,预留 1 回;本期 3 回,分别为 22020塘厦变、庙前变、朋口变各 1 回。 35kV:远景 6 回,分别为庙前线、冶炼线、朋口线、新工线、莒溪线、新联线各 1 回;本期建设3 回,分别为庙前线、冶炼线、莒溪线各 1 回。 10kV:远景24 回;本期 8 回。 3、无功补偿 10kV 电容器容量:远景6×4.0Mvar,本期 2×4.0M...