XXXXXXXXXXX XXXXXXXXXXX 项目 赶工费计算书 项目名称:XXXXXXXXXXX 建设单位:XXXXXXXXXXX 施工单位:XXXXXXXXXXX 编制单位:XXXXXXXXXXX 工程造价:(小写) XXXXXXXXXXX 元 (大写): XXXXXXXXXXX 编制人: 编制时间: XXXXXXXXXXX 第 1 页 共 1 5 页 目 录 目 录 ........................................................................................................................................................................1 一、赶工背景 ............................................................................................................................................................2 二、赶工理论支撑 ....................................................................................................................................................3 三、实际赶工布署 ....................................................................................................................................................3 四、实际赶工布署的响应 ........................................................................................................................................5 五、赶工费的计算 ....................................................................................................................................................5 1、直接发生的人工密集作业及管理人员的投入 ...........................................................................................6 (1)新增管理人员费用 ..............................................................................................................................6 (2)新增劳务作业人员费用 ......................................................................................................................6 2、周转材料不按照正常摊销的投入增加.......................................................................................................7 3、因赶工而增加超出正常的施工机械投入......................................................................................................