地铁暗挖车站土方开挖施工作业指导 第一篇:地铁暗挖车站土方开挖施工作业指导 厦门市轨道交通 2 号线一期工程土建 2 标 【建业路站、湖滨中路站、体育中心站、育秀东路站】 地铁暗挖车站土方施工作业 指导书 编制: 审核: 审批: 厦门市轨道 2 号线二标项目部 二 O 一五年八月 厦门市轨道 2 号线二标 施工作业指导书 名目 1 编制目的〔黑体四号〕 ···························································································2 编制根据 ·············································································································3 适 用 范 围 ·············································································································4 施工方法及工艺要求 ······························································································ 4.1施工工艺流程 ······························································································· 4.2. 施工方法 ··································································································5 质量保证措施 ·······································································································6 平安、文明施工保证措施 ·······················································...