市政工程施工交通组织方案范文目录一、工程概况····························································2 二、交通的目标···················································2 三、施工方案····························································2 四、交通的原则···················································3 五、封闭及疏导方案·············································4 六、保障措施····························································8济南市二环南路兴隆大沟桥维修加固工程组织方案一、工程概况兴隆大沟桥位于济南市二环南路,桥梁全长 46
4m,桥面宽 48m,横向布置为3
5m(人行道)+41m(车行道)+3
5m(人行道)
此次工程设计为对桥面板进行更换,采纳交通部现行公路一级 13m 标准板
原墩台帽进行拆除按现行设计标准重做
更换桥梁板式橡胶支座,重新铺设人行道及安装新栏杆,加铺一层钢筋混凝土层,重新铺设桥面防水层和沥青混凝土桥面铺装
由于现场交通较为复杂,交通压力较大,本工程需半幅封闭施工,半幅开放交通
现状交通二、交通组织的目标我公司在施工期间交通组织的目标是:“在确保交通稳定畅通的前提下,各项工序协调进展,最终如期竣工
”三、施工方案 1、工期:总工期 90 天
2、总体施工安排:先施工慢车道及人行道,后施工快车道(先施工两侧,后施工中间)
组织好各工序的衔接,保证对交通的影响降到最低
3、交通设施的设置 3