前 言本次桥面系技术交底工作是结合项目实际情况,对一些桥面系施工相关的精细化施工予以强调与明确。 目 录1 施工工序...............................................................................................................................31.1 铺装前梁板粗糙度处理...............................................................................................31.2 面板清理.......................................................................................................................31.3 放样及绑扎钢筋焊网...................................................................................................41.4 轨道安装.......................................................................................................................41.5 混凝土摊铺...................................................................................................................61.6 混凝土收面...................................................................................................................71.7 混凝土收面...................................................................................................................81.8 桥面麻面处理...............................................................................................................81.9 悬挂式刻纹机...............................................................................................................81 施工工序1.1 铺装前梁板粗糙度处理1.1.1 通常架梁之前,梁板经过拉毛或刷毛处理,若表面粗糙度不够,会影响上面混凝土铺装层的粘结力,所以架梁之后,我们使用小型铣刨机或气动凿毛机进行机械凿毛处理,去除梁板的浮浆,使其表面达到一定粗糙度,增加其粘结力。1.1.2 梁板上的门筋稀密程度不等,可根据门筋的间隙选择铣刨机或凿毛机的型号,门筋间隙小的可用 250 型铣刨机或 11 头凿毛机,门筋间隙大的可选用 300 型或350 型铣刨机,做到去除浮浆,露出粗糙表面,达到与混凝土再次结合的目的。 铣刨效果图 梁板凿毛效果1.2 面板清理1.2.1 将铣刨或凿毛后的浮浆,用吹风机清理洁净。背负式吹风机1.3 放样及绑扎钢筋焊网1...