九州通大厦一期地下室基坑工程施工组织设计湖北广元岩土工程有限公司二○一一年四月二十五日九州通大厦一期地下室基坑工程施工组织设计项目经理:谢俊技术负责:王继坤审核:李三明编制:张方方日期:二○一一年四月二十五日目录第一章工程概况...............................................................................................31.1工程概述..................................................................................................31.2基坑支护方案..........................................................................................4第二章施工准备...............................................................................................52.1施工技术准备..........................................................................................52.2施工场地准备..........................................................................................52.3材料准备..................................................................................................52.4劳动力准备..............................................................................................6第三章项目组织架构.......................................................................................73.1施工组织机构..........................................................................................73.2项目管理机构配备..................................................................................9第四章用于本项目主要施工机械明细表.....................................................12第五章主要施工方法.....................................................................................135.1工程测量................................................................................................135.2钻孔灌注钢柱桩工程............................................................................135.3钻孔灌注支护桩工程............................................................................195.4人工挖孔支护桩工程............................................................................205.5土钉挂网喷砼工程................................................................................245.6冠梁、内支撑梁工程............................................................................285.7抗浮锚杆工程........................................................................................315.8施工监测及应急措施............................................................................335.9土方开挖施工配合要求........................................................................36第六章施工进度计划.....................................................................................396.1施工总工期............................................................................................3916.2施工总进度控制方法............................................................................396.3施工进度总计划图................................................................................406.4里程碑时间............................................................................................40第七章保证工程质量的技术措施.................................................................43第八章确保施工工期的技术措施.................................................................52第九章确保安全的技术组织措施.................................................................55第十章施工总平面布置...............