第1页共56页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第1页共56页施工组织方施工组织方案案第2页共56页第1页共56页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第2页共56页目录目录···························································································1第一章编制说明····························································51.编制原则·································································································52.关于施工工期及范围·················································································53.关于工程进度···························································································54.备注说明·································································································5第二章编制依据····························································6第三章工程概况····························································6第四章需要建设方的配合条件····························61.施工前的配合要求····················································································62.不可预见的协调·······················································································6第五章总体施工方案·················································71.总体施工·································································································71.1.前端工程········································································································71.2.设备安装调试工程··························································································71.3.总体管理措施·································································································82.施工准备·································································································82.1.施工管理制度的建立·············································...