长汀县2016年危桥改造项目实施性施工组织设计福建神通建设工程有限公司二0一六年十月长汀县2016年危桥改造项目实施性施工组织设计编制人:复核人:福建神通建设工程有限公司长汀县2016年危桥改造项目经理部二0一六年十月二日目录第一章编制依据及指导思想.............................................................................................................................1第一节、编制依据·········································································································································1第二节、指导思想·········································································································································2第二章编制说明.................................................................................................................................................2一、设计标准·················································································································································2二、主要工程数量·········································································································································7第三章施工安排.................................................................................................................................................8第一节、施工要点及施工方案·····················································································································8第二节、设备、人员动员周期和设备、人员、材料运到·······································································10一、设备、人员动员周期···················································································································11二、设备、人员、材料运到施工现场的方法···················································································12三、本工程施工队及施工任务安排·································································································12四、拟安排本工程主要施工设备·····································································································12五、资金使用计划···········································...