延安市场沟34楼#2013年3月施工组织设计薛利亚延安昌新建筑有限责任公司第1页共95页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第1页共95页目录1.编制说明及编制依据...................................................................................................................41.1编制依据·······························41.2编制说明·······························42.工程概况及特点...........................................................................................................................42.1总述·································42.2现场概况·······························52.3本项目工程施工目标··························52.3.1质量目标:······························52.3.2进度目标:······························52.3.3安全目标:······························52.4本工程的重点及难点··························53.项目组织管理机构.......................................................................................................................63.1项目及主要管理人员简历························103.1.1项目经理简历表···························103.1.2技术负责人简历表··························113.1.3项目质量负责人简历表························123.1.4项目安全负责人简历表························123.1.5主要施工管理人员简历表·······················133.1.6单位基本情况表···························143.2项目经理部管理机构职责划分·······················154.总平面图.....................................................................................................................................175.施工临时用水用电施工方案.....................................................................................................175.1临时用水施工方案····························175.2临时用电施工方案····························195.3临时道路及硬覆盖施工方案························23第2页共95页第1页共95页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第2页共95页6.施工进度计划及劳动力安排.....................................................................................................246.1施工段划分及施工程序··························246.2总工期及进度计划安排··························246.3工期保证措施······························246.3.1组织措施:·····························246.3.2管理措施:·····························256.3.3经济措施:·····························256.3.4技术措施:·····························256.4劳动力数量及进场计划··························267.施工机械设备.............................................................................................................................278.施工方案及施...