第1页共93页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第1页共93页目录1、编制依据和原则··················31.1编制依据·····················31.2编制原则·····················32、工程概况······················32.1工程项目简介···················32.2标段概况·····················42.3周围环境及地质特征················42.4气象和水文特征··················52.5交通情况·····················52.6资源供应情况···················53、施工组织机构····················53.1总部·······················53.2现场·······················53.3工点·······················54、各分部分项工程施工方案及保证质量措施·······74.1河道工程施工方案·················74.1.1河道工程总体施工顺序··············74.1.2围堰及拆除围堰方案···············84.1.3河床清淤方案··················10第2页共93页第1页共93页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第2页共93页4.1.4直立式复合河堤施工方案·············124.1.5桩承式河堤施工方案···············164.2排水工程施工方案················204.2.1排水工程施工顺序················204.2.2沟槽开挖····················214.2.3管道铺设····················224.2.4回填······················224.3道路工程施工方案················224.3.1道路工程总体施工顺序··············234.3.2道路工程施工方法················234.4质量保证措施··················244.4.1道路工程施工质量保证措施···········244.4.2排水工程施工质量保证措施···········264.4.3河道工程施工质量保证措施···········275、施工现场平面布置·················285.1施工现场平面布置原则···············285.2施工现场平面布置方案···············285.3施工总平面布置图·················296、冬雨季施工措施··················316.1冬雨季施工工期保证措施··············316.2冬雨季施工质量保证措施··············31第3页共93页第2页共93页编号:时间:2021年x月x日书山有路勤为径,学海无涯苦作舟页码:第3页共93页7、初步施工进度计划和工期保证措施··········337.1初步施工进度计划·················337.2工期保证措施···················368、质量保证体系···················378.1组织保证·····················378.2制度保证·····················408.3过程控制·····················429、安全保证体系及措施················439.1安全保证体系···················439.2保证安全措施···················4610、文明施工措施···················4911、环境保护措施···················5112、消防、治安保证措施················5313、交通保障措施···················5414、成林树木保护措施·················5415、采用新技术、新工艺、新材料的实施意见······55...