卧式水轮发电机组安装工艺Horizontalhydro-generatingunitinstallationprocess卧式水轮发电机组的安装分为预埋部份(管路)、导水机构(主机)、轴承部份、基础部份、发电机部份、辅助设备
Theinstallationofthehorizontalhydro-generatingunitisdividedintoembeddedpart(piping),distributor(mainunit),bearingpart,foundationpart,generatorpart,auxiliarypart
一、水轮发电机组埋件预埋Hydro-generatingunitembeddedpart根据工程进度的要求与土建配合对所需的油、气、水管路进行预埋,对所有埋设的管路的管口进行封堵,防止异物进入
Embedtheneededoil,gas,waterpipingaccordingtotheprojectprocessandcivilengineering
Plugallthepipeorificesofthepipingembeddedtokeepforeignmattersfromgettinginto
二、测点放样Measuringpointlayout根据按甲方提供的高程按设计图纸来确定机组的三维坐标,方法可用水准仪或钢琴线连通器原理来保证机组中心、高程与X、Y坐标
Accordingtotheheightprovidedbyownerandthedesigndrawingtodeterminetheunitthree-dimensioncoordinate,andtheunitcenter,heightandX、Ycoordinatecanbeguaranteedwithbalancelevelorthelawofpianolin